Yagan Square

Project: Yagan Square
Location: Yagan Square
Type: Shop fitting
Builder: OPRA Projects

Scope of works:

This project commenced during the final stages of the base-building works for the wider Yagan Square development. Working alongside OPRA Projects we were required to coordinate between OPRA and base-builders requirements, further adding to the technicalities of working in a live and public facing environment.

Base-building delays hindered the already challenging time frame and many design changes were made due to a high level of client and design-team involvement. WAPE remained flexible, ensuring requested changes were made and time absorbed, where possible, into the already challenging programme.

Services provided:

  • Complete electrical fit outs to:
    • Lena Lu
    • Toast my curry
    • The Shoe
    • Fish Boss
    • Sue Lewis Chocolatier
  • Supplied & installed electrical switchboards, switches, controls, and switchgear protection
  • Installed complete wiring system for lighting, emergency lighting, power, communications & 3rd party lighting control
  • Cable pathways, enclosures and materials
  • Power supplies to fixed appliances and equipment.
  • Supplied & installed single point Emergency and Exit Lighting System complete with emergency test switch.
  • Cat6 structured communications installation including a new 45ru communications rack to house communications, audio & security accessories
  • Co-ordinated and interfaced with the Head Contractors’ commissioning programme and with all other trades.
  • Co-ordinated with door interface trades to ensure that power requirements were appropriate.
  • All final sub circuits.
  • As constructed documentation & operation manuals.